Wind power and windfarms database
Greensolver

English English Deutsch Espa˝ol


Eoltech

Online access > Wind farms > Cuxhaven (Germany)


[Back to previous page]

Generalities

PDF

Details



Part #1:

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 8,030 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #2:

  • City: Cuxhaven
  • Commissioning: 2006/12
  • 1 turbine: Repower 5M (power 5 000 kW, diameter 126 m)
  • Hub height: 117 m
  • Total nominal power: 5,000 kW
  • Operational
  • Onshore wind farm
  • Developer: Senvion
  • Operator: EWE
  • Owners: E.ON Climate Renewables/RWE

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 16,050 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #3:

  • City: Cuxhaven
  • Commissioning: 2006
  • 1 turbine: Repower 5M (power 5 000 kW, diameter 126 m)
  • Hub height: 117 m
  • Total nominal power: 5,000 kW
  • Operational
  • Onshore wind farm
  • Developer: Senvion
  • Operator: RWE
  • Owner: EWC Windpark Cuxhaven GmbH

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 12.7 %
  • Expected production: 15,190 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #4:

  • City: Cuxhaven
  • Commissioning: 1994/06
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 450 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 1,440 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #5:

  • City: Cuxhaven
  • Commissioning: 1999/09
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 1,000 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 3,210 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #6:

  • City: Cuxhaven
  • Commissioning: 2008/12
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 1,300 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 14.9 %
  • Expected production: 4,650 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #7:

  • City: Cuxhaven
  • Commissioning: 1996/07
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 600 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 1,930 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #8:

  • City: Cuxhaven
  • Commissioning: 1991
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 150 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 480 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #9:

  • Part: Cuxhaven-Altenbruch
  • City: Cuxhaven
  • Commissioning: 2001
  • 16 turbines: (manufacturer name not available)
  • Total nominal power: 20,800 kW
  • Operational
  • Onshore wind farm
  • Developer: PNE

       Production forecast

  • From Monday, September 26 2016, 02:00 UTC, for the coming 24 hours:
  • Expected load rate: 13.4 %
  • Expected production: 66,780 kWh
  • Values from Climpact-Metnext Windcaster solution

Localisation



Part #1:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #2:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #3:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #4:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #5:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #6:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #7:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #8:

  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Part #9:

  • Part: Cuxhaven-Altenbruch
  • Latitude: 53░ 51' 42.1"
  • Longitude: 8░ 41' 38.6"
  • Geodetic system: WGS84
  • Precise localization: no

Global map




Pictures



No photos for this wind farm.

Update for this sheet: /
Complete/correct this sheet:


www.thewindpower.net - 2005-2016 - all rights reserved - contact - partners - advertising