Tolstrup windfarm (Denmark)
[Back to previous page]
Generalities
- Wind farm name: Tolstrup
- Country: Denmark
- Total power: 9 MW
- Estimated annual production: 23 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- City: Tolstrup
- Commissioning: 1988/07
- 0 turbine(s) Nordtank
- Hub height: 26 m
- Total nominal power: 0 kW
- Dismantled
- Onshore wind farm
Part #2:
- City: Tolstrup
- Commissioning: 2009/07
- 4 turbine(s) Siemens SWT-2.3-93 (power 2300 kW, diameter 93 m)
- Hub height: 80 m
- Total nominal power: 9,200 kW
- Operational
- Onshore wind farm
Part #3:
- City: Tolstrup
- Commissioning: 1987/10
- 0 turbine(s) Bonus
- Total nominal power: 0 kW
- Dismantled
- Onshore wind farm
Part #4:
- City: Tolstrup
- Commissioning: 1989/08
- 0 turbine(s) Bonus
- Total nominal power: 0 kW
- Dismantled
- Onshore wind farm
Update for this sheet: 02/2013
Complete/correct this sheet: contact page