Generalities
- Wind farm name: Victory Garden
- Country: USA
- County / Zone: California
- Total power: 7 MW
- Estimated annual production: 16 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- City: Tehachapi
- Commissioning: 2005
- 1 turbine(s) Vestas
- Total nominal power: 660 kW
- Operational
- Onshore wind farm
- Developed by: Caithness
- Operator: Caithness
- Owner: Caithness
Part #2:
- City: Tehachapi
- Commissioning: 2005
- 8 turbine(s) Zond
- Total nominal power: 6,000 kW
- Operational
- Onshore wind farm
- Developed by: Caithness
- Operator: Caithness
- Owner: Caithness
Update for this sheet: 02/2011
Complete/correct this sheet: contact page