Generalities
- Wind farm name: Hopsten I
- Country: Germany
- County / Zone: Nordrhein-Westfalen
- Total power: 2 MW
- Estimated annual production: 5 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
- Commissioning: 2000/12
- 2 turbine(s) Enercon E58/1000 (power 1000 kW, diameter 58 m)
- Hub height: 70 m
- Total nominal power: 2,000 kW
- Operational
- Onshore wind farm
- Operator: Natenco
Update for this sheet: 02/2011