Generalities
- Wind farm name: Bad Meinberg
- Country: Germany
- County / Zone: Nordrhein-Westfalen
- Total power: 7 MW
- Estimated annual production: 18 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- Commissioning: 1997
- 3 turbine(s) (manufacturer name not available)
- Total nominal power: 1,800 kW
- Operational
- Onshore wind farm
Part #2:
- 4 turbine(s) (manufacturer name not available)
- Total nominal power: 1,930 kW
- Operational
- Onshore wind farm
Part #3:
- Commissioning: 1998
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 600 kW
- Operational
- Onshore wind farm
Part #4:
- Commissioning: 1995
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 500 kW
- Operational
- Onshore wind farm
Part #5:
- Commissioning: 1998/12
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 2,000 kW
- Operational
- Onshore wind farm
Part #6:
- Commissioning: 1997/11
- 1 turbine(s) Dewind D4 (power 600 kW, diameter 48 m)
- Hub height: 70 m
- Total nominal power: 600 kW
- Operational
- Onshore wind farm
Update for this sheet: 09/2010