Fæbæk windfarm (Denmark)
[Back to previous page]
Generalities
- Wind farm name: Fæbæk
- Country: Denmark
- Total power: 1 MW
- Estimated annual production: 2 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- Commissioning: 1996/09
- 1 turbine(s) Neg Micon
- Hub height: 35 m
- Total nominal power: 500 kW
- Operational
- Onshore wind farm
Part #2:
- Commissioning: 1990/07
- 0 turbine(s) Neg Micon
- Hub height: 35 m
- Total nominal power: 0 kW
- Dismantled
- Onshore wind farm
Part #3:
- Commissioning: 1998/04
- 1 turbine(s) Bonus B31/300 (power 300 kW, diameter 31 m)
- Hub height: 30 m
- Total nominal power: 300 kW
- Operational
- Onshore wind farm
Part #4:
- Commissioning: 1990/08
- 1 turbine(s) Neg Micon
- Hub height: 32.5 m
- Total nominal power: 150 kW
- Operational
- Onshore wind farm
Part #5:
- Commissioning: 1989/09
- 0 turbine(s) Neg Micon
- Hub height: 32.5 m
- Total nominal power: 0 kW
- Dismantled
- Onshore wind farm
Update for this sheet: 12/2010
Complete/correct this sheet: contact page