Warendorf windfarm (Germany)
[Back to previous page]
Generalities
- Wind farm name: Warendorf
- Country: Germany
- County / Zone: Nordrhein-Westfalen
- Total power: 26 MW
- Estimated annual production: 64 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- Commissioning: 1998/01
- 1 turbine(s) Dewind D4 (power 600 kW, diameter 48 m)
- Hub height: 70 m
- Total nominal power: 600 kW
- Operational
- Onshore wind farm
Part #2:
- Commissioning: 2002/01
- 1 turbine(s) Dewind D6 (power 1250 kW, diameter 64 m)
- Hub height: 91.5 m
- Total nominal power: 1,250 kW
- Operational
- Onshore wind farm
Part #3:
- 3 turbine(s) (manufacturer name not available)
- Total nominal power: 1,800 kW
- Operational
- Onshore wind farm
Part #4:
- Commissioning: 2009
- 11 turbine(s) (manufacturer name not available)
- Total nominal power: 22,000 kW
- Operational
- Onshore wind farm
Update for this sheet: 10/2010
Complete/correct this sheet: contact page