Generalities

  • Wind farm name: Campolieto
  • Country: Italy
  • County / Zone: Molise
PDF

Details


Part #1:

  • City: Campolieto
  • 3 turbines: (manufacturer name not available)
  • Total nominal power: 1,980 kW
  • Operational
  • Onshore wind farm
  • Operator: Enel GreenPower

       Production forecast

  • From Tuesday, February 28 2017, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 70.3 %
  • Expected production: 33,390 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #2:

  • City: Campolieto
  • 3 turbines: (manufacturer name not available)
  • Total nominal power: 1,980 kW
  • Operational
  • Onshore wind farm
  • Operator: Enel GreenPower

       Production forecast

  • From Tuesday, February 28 2017, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 70.3 %
  • Expected production: 33,390 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #3:

  • City: Campolieto
  • 3 turbines: (manufacturer name not available)
  • Total nominal power: 1,980 kW
  • Operational
  • Onshore wind farm
  • Operator: Enel GreenPower

       Production forecast

  • From Tuesday, February 28 2017, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 70.3 %
  • Expected production: 33,390 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #4:

  • City: Campolieto
  • 12 turbines: (manufacturer name not available)
  • Total nominal power: 10,200 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, February 28 2017, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 70.3 %
  • Expected production: 172,000 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #5:

  • City: Campolieto
  • Commissioning: 2001
  • 4 turbines: Neg Micon NM48/750 (power 750 kW, diameter 48.2 m)
  • Total nominal power: 3,000 kW
  • Operational
  • Onshore wind farm
  • Operator: Enel GreenPower

       Production forecast

  • From Tuesday, February 28 2017, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 63.1 %
  • Expected production: 45,430 kWh
  • Values from Climpact-Metnext Windcaster solution

Localisation


Part #1:

  • Latitude: 41░ 37' 48"
  • Longitude: 14░ 46' 11.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #2:

  • Latitude: 41░ 37' 48"
  • Longitude: 14░ 46' 11.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #3:

  • Latitude: 41░ 37' 48"
  • Longitude: 14░ 46' 11.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #4:

  • Latitude: 41░ 37' 48"
  • Longitude: 14░ 46' 11.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #5:

  • Latitude: 41░ 37' 48"
  • Longitude: 14░ 46' 11.9"
  • Geodetic system: WGS84
  • Precise localization: no

Global map



Pictures


No photos for this wind farm.

Update for this sheet: 09/2015