  • City: Jeréz de la Frontera 
  • Commissioning: 2009
  • 13 turbines: Ecotecnia 80 1.6 (power 1 670 kW, diameter 80 m)
  • Total nominal power: 21,710 kW
  • Operational
  • Onshore wind farm
  • Developer: Gecal SA
  • Operator: Gecal SA
  • Owner: Gecal SA

       Production forecast

  • From Wednesday, December 07 2016, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 12.9 %
  • Expected production: 67,470 kWh
  • Values from Climpact-Metnext Windcaster solution

Localisation

  • Latitude: 36° 41' 11.6"
  • Longitude: -6° 8' 13.8"
  • Geodetic system: WGS84
  • Precise localization: no