Part #1:
- Part: Part 1
- City: Xique-Xique
- Turbine(s): (manufacturer name not available)
- Total nominal power: 36,000 kW
- Under construction
- Onshore wind farm
- Operator: Omega
Part #2:
Part #3:
- Part: Part 1-III
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 12,500 kW
- Operational
- Onshore wind farm
- Operator: Omega
- Owner:
- Source:
Part #4:
- Part: Part 1-IV
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 30,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
- Owner:
- Source:
Part #5:
Part #6:
Part #7:
- Part: Part 2
- City: Xique-Xique
- Turbine(s): (manufacturer name not available)
- Total nominal power: 31,500 kW
- Under construction
- Onshore wind farm
- Operator: Omega
Part #8:
- Part: Part 2 - Capoeiras 3
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 28,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #9:
- Part: Part 2 - Curral de Pedras 1
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 20,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #10:
- Part: Part 2 - Curral de Pedras 2
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 28,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #11:
- Part: Part 2 - Diamante 2
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 18,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #12:
- Part: Part 2 - Diamante 3
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 18,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #13:
- Part: Part 3
- City: Xique-Xique
- Turbine(s): (manufacturer name not available)
- Total nominal power: 36,000 kW
- Under construction
- Onshore wind farm
- Operator: Omega
Part #14:
- Part: Part 3 - Laranjeiras 1
- City: Xique
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 28,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #15:
- Part: Part 3 - Laranjeiras 2
- City: Xique
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 30,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #16:
- Part: Part 3 - Laranjeiras 3
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 25,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #17:
- Part: Part 3 - Laranjeiras 5
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 25,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #18:
- Part: Part 3 - Laranjeiras 9
- City: Gentio do Ouro
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 25,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #19:
- Part: Part 4
- City: Xique-Xique
- Turbine(s): (manufacturer name not available)
- Total nominal power: 36,000 kW
- Under construction
- Onshore wind farm
- Operator: Omega
Part #20:
- Part: Part 5
- City: Xique-Xique
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 36,000 kW
- Operational
- Onshore wind farm
- Operator: Omega
Part #21:
- Part: Part 5 - 3
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 31,500 kW
- Operational
- Onshore wind farm
- Operator: Omega
- Owner:
Part #22:
- Part: Part 5 - 5
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 40,500 kW
- Operational
- Onshore wind farm
- Operator: Omega
- Owner:
Part #23:
- Part: Part 5 - 6
- Commissioning:
- Turbine(s): (manufacturer name not available)
- Total nominal power: 22,500 kW
- Operational
- Onshore wind farm
- Operator: Omega
- Owner:
Part #24:
- Part: Part 6
- City: Xique-Xique
- Turbine(s): (manufacturer name not available)
- Total nominal power: 36,000 kW
- Under construction
- Onshore wind farm
- Operator: Omega
Localisation
Part #1:
- Part: Part 1
- Latitude: -11° 1' 30"
- Longitude: -42° 38' 27.5"
- Geodetic system: WGS84
- Precise localization: no
Part #2:
- Part: Part 1-II
- Latitude: -11° 9' 49.6"
- Longitude: -42° 40' 14.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #3:
- Part: Part 1-III
- Latitude: -11° 10' 14"
- Longitude: -42° 40' 52.7"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #4:
- Part: Part 1-IV
- Latitude: -11° 2' 50.9"
- Longitude: -42° 41' 15.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #5:
- Part: Part 1-V
- Latitude: -11° 11' 2.7"
- Longitude: -42° 42' 19.1"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #6:
- Part: Part 1-VII
- Latitude: -11° 4' 15.7"
- Longitude: -42° 40' 43.7"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #7:
- Part: Part 2
- Latitude: -11° 2' 9.5"
- Longitude: -42° 36' 54"
- Geodetic system: WGS84
- Precise localization: no
Part #8:
- Part: Part 2 - Capoeiras 3
- Latitude: -11° 10' 33.9"
- Longitude: -42° 44' 18.9"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #9:
- Part: Part 2 - Curral de Pedras 1
- Latitude: -11° 8' 2"
- Longitude: -42° 39' 15.4"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #10:
- Part: Part 2 - Curral de Pedras 2
- Latitude: -11° 12' 42.4"
- Longitude: -42° 42' 4.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #11:
- Part: Part 2 - Diamante 2
- Latitude: -11° 6' 20.1"
- Longitude: -42° 40' 23.1"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #12:
- Part: Part 2 - Diamante 3
- Latitude: -11° 5' 25.4"
- Longitude: -42° 40' 58.7"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #13:
- Part: Part 3
- Latitude: -11° 3' 36"
- Longitude: -42° 37' 51.6"
- Geodetic system: WGS84
- Precise localization: no
Part #14:
- Part: Part 3 - Laranjeiras 1
- Latitude: -11° 7' 22"
- Longitude: -42° 41' 2.7"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #15:
- Part: Part 3 - Laranjeiras 2
- Latitude: -11° 7' 46.9"
- Longitude: -42° 41' 54.6"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #16:
- Part: Part 3 - Laranjeiras 3
- Latitude: -11° 2' 7.4"
- Longitude: -42° 37' 55.5"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #17:
- Part: Part 3 - Laranjeiras 5
- Latitude: -11° 6' 52.1"
- Longitude: -42° 40' 15.9"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #18:
- Part: Part 3 - Laranjeiras 9
- Latitude: -11° 4' 52.3"
- Longitude: -42° 37' 4.8"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #19:
- Part: Part 4
- Latitude: -10° 49' 18.1"
- Longitude: -42° 43' 35.7"
- Geodetic system: WGS84
- Precise localization: no
Part #20:
- Part: Part 5
- Latitude: -11° 6' 25.1"
- Longitude: -42° 37' 44.3"
- Geodetic system: WGS84
- Precise localization: no
Part #21:
- Part: Part 5 - 3
- Latitude: -11° 1' 8.4"
- Longitude: -42° 40' 37.1"
- Geodetic system: WGS84
- Precise localization: no
Part #22:
- Part: Part 5 - 5
- Latitude: -11° 7' 58.7"
- Longitude: -42° 37' 51.6"
- Geodetic system: WGS84
- Precise localization: no
Part #23:
- Part: Part 5 - 6
- Latitude: -11° 6' 3.6"
- Longitude: -42° 41' 56.3"
- Geodetic system: WGS84
- Precise localization: no
Part #24:
- Part: Part 6
- Latitude: -11° 3' 57.6"
- Longitude: -42° 36' 10.8"
- Geodetic system: WGS84
- Precise localization: no
Update for this sheet: 8 November 2023