[Back to previous page]
Generalities
|
|
Details
Part #1:
- City: Bobbau
- Commissioning:

- 5 turbines: Dewind D8.0 (power 2 000 kW, diameter 80 m)
- Hub height:

- Total nominal power: 10,000 kW
- Operational
- Onshore wind farm
Production forecast
- From Monday, January 18 2021, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 27.4 %
- Expected production: 65,640 kWh
- Values from Weathernews Windcaster solution
Part #2:
- City: Bobbau
- Commissioning:

- 5 turbines: GE Energy 1.5sl (power 1 500 kW, diameter 77 m)
- Hub height:

- Total nominal power: 7,500 kW
- Operational
- Onshore wind farm
- Developer: Enertrag
Production forecast
- From Monday, January 18 2021, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 31.2 %
- Expected production: 56,170 kWh
- Values from Weathernews Windcaster solution
Part #3:
- City: Bobbau
- Commissioning:

- 1 turbine: (manufacturer name not available)
- Total nominal power: 2,300 kW
- Operational
- Onshore wind farm
Production forecast
- From Monday, January 18 2021, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 38.3 %
- Expected production: 21,140 kWh
- Values from Weathernews Windcaster solution
Localisation
Part #1:
- Latitude: 51° 41' 26.3"
- Longitude: 12° 15' 53.6"
- Geodetic system: WGS84
- Precise localization: no
Part #2:
- Latitude: 51° 42' 2.9"
- Longitude: 12° 13' 27"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #3:
- Latitude: 51° 41' 26.3"
- Longitude: 12° 15' 53.6"
- Geodetic system: WGS84
- Precise localization: no
Update for this sheet: 2 July 2015
Complete/correct this sheet: