Kergrist windfarm (France)
[Back to previous page]
Generalities
- Wind farm name: Kergrist
- Country: France
- County / Zone: 56
- Total installed power: 11.1 MW
- Estimated annual production: 27 GW.h (for an equivalent of 2500 hours of full load/year)
Details
Part #1:
- Part: Le Roduel
- City: Kergrist
- Commissioning: 2006/01
- 1 turbine(s) Vestas V52/850 (power 850 kW, diameter 52 m)
- Total nominal power: 850 kW
- Operational
- Onshore wind farm
- Developed by: P&T Technologie
- Operator: Iberdrola
- Owner: IER
Part #2:
- Part: Le Roduel
- City: Kergrist
- Commissioning: 2006/01
- 3 turbine(s) Vestas V80/1800 (power 1800 kW, diameter 80 m)
- Hub height: 78 m
- Total nominal power: 5400 kW
- Operational
- Onshore wind farm
- Developed by: P&T Technologie
- Operator: Iberdrola
- Owner: IER
Part #3:
- Part: Lérôme
- City: Kergrist
- Commissioning: 2005/12
- 1 turbine(s) Vestas V52/850 (power 850 kW, diameter 52 m)
- Hub height: 60 m
- Total nominal power: 850 kW
- Operational
- Onshore wind farm
- Developed by: P&T Technologie
- Operator: Iberdrola
- Owner: IER
Part #4:
- Part: Lérôme
- City: Kergrist
- Commissioning: 2005/12
- 2 turbine(s) Vestas V80/2000 (power 2000 kW, diameter 80 m)
- Hub height: 100 m
- Total nominal power: 4000 kW
- Operational
- Onshore wind farm
- Developed by: P&T Technologie
- Operator: Iberdrola
- Owner: IER
Update for this sheet: 08/2011
Complete/correct this sheet: contact page