Generalities
- Wind farm name: Bedburg-Hau
- Country: Germany
- County / Zone: Niedersachsen
- Total power: 3 MW
- Estimated annual production: 8 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- Commissioning: 1994/04
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 110 kW
- Operational
- Onshore wind farm
Part #2:
- Commissioning: 1999/03
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 750 kW
- Operational
- Onshore wind farm
Part #3:
- Commissioning: 2001/08
- 1 turbine(s) Nordex N80/2500 (power 2500 kW, diameter 80 m)
- Total nominal power: 2,500 kW
- Operational
- Onshore wind farm
Update for this sheet: 01/2011
Complete/correct this sheet: contact page