Beverungen windfarm (Germany)
[Back to previous page]
Generalities
- Wind farm name: Beverungen
- Country: Germany
- County / Zone: Nordrhein-Westfalen
- Total power: 22 MW
- Estimated annual production: 55 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 160 kW
- Operational
- Onshore wind farm
Part #2:
- 4 turbine(s) (manufacturer name not available)
- Total nominal power: 4,000 kW
- Operational
- Onshore wind farm
Part #3:
- 5 turbine(s) (manufacturer name not available)
- Total nominal power: 1,250 kW
- Operational
- Onshore wind farm
Part #4:
- 3 turbine(s) (manufacturer name not available)
- Total nominal power: 4,500 kW
- Operational
- Onshore wind farm
Part #5:
- 3 turbine(s) (manufacturer name not available)
- Total nominal power: 2,400 kW
- Operational
- Onshore wind farm
Part #6:
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 150 kW
- Operational
- Onshore wind farm
Part #7:
- 5 turbine(s) (manufacturer name not available)
- Total nominal power: 3,000 kW
- Operational
- Onshore wind farm
Part #8:
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 300 kW
- Operational
- Onshore wind farm
Part #9:
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 450 kW
- Operational
- Onshore wind farm
Part #10:
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 4,000 kW
- Operational
- Onshore wind farm
Part #11:
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 1,800 kW
- Operational
- Onshore wind farm
Update for this sheet: 09/2010
Complete/correct this sheet: contact page