- Total power: 13 MW
- Estimated annual production: 32 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 300 kW
- Operational
- Onshore wind farm
Part #2:
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 1,200 kW
- Operational
- Onshore wind farm
Part #3:
- Commissioning: 2000
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 1,500 kW
- Operational
- Onshore wind farm
Part #4:
- Commissioning: 2007/04
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 4,000 kW
- Operational
- Onshore wind farm
Part #5:
- Commissioning: 1994/03
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 450 kW
- Operational
- Onshore wind farm
Part #6:
- Commissioning: 1995
- 4 turbine(s) (manufacturer name not available)
- Total nominal power: 2,000 kW
- Operational
- Onshore wind farm
Part #7:
- Commissioning: 2006
- 1 turbine(s) (manufacturer name not available)
- Total nominal power: 1,800 kW
- Operational
- Onshore wind farm
Part #8:
- Commissioning: 2006/04
- 2 turbine(s) (manufacturer name not available)
- Total nominal power: 1,600 kW
- Operational
- Onshore wind farm
Update for this sheet: 10/2010