Görike-Söllenthin windfarm (Germany)
[Back to previous page]
Generalities
- Wind farm name: Görike-Söllenthin
- Country: Germany
- County / Zone: Brandenburg
- Total power: 30 MW
- Estimated annual production: 73 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- City: Görike
- Commissioning: 2003
- 5 turbine(s) Repower MM70 (power 2000 kW, diameter 70 m)
- Hub height: 65 m
- Total nominal power: 7,500 kW
- Operational
- Onshore wind farm
- Developed by: WPD
Part #2:
- City: Görike
- Commissioning: 2002
- 8 turbine(s) Repower MM70 (power 2000 kW, diameter 70 m)
- Hub height: 65 m
- Total nominal power: 12,000 kW
- Operational
- Onshore wind farm
- Developed by: WPD
Part #3:
- Commissioning: 2010
- 5 turbine(s) Vestas V90/2000 (power 2000 kW, diameter 90 m)
- Total nominal power: 10,000 kW
- Operational
- Onshore wind farm
- Developed by: PNE
- Operator: PNE
- Owner: EnBW Energie
Update for this sheet: 05/2012
Complete/correct this sheet: contact page