Generalities
- Wind farm name: Horsted
- Country: Denmark
- Total power: 2 MW
- Estimated annual production: 4 GW.h (for an equivalent of 2,500 hours of full load/year)
Details
Part #1:
- City: Horsted
- Commissioning: 1997/05
- 2 turbine(s) Vestas V44/600 (power 600 kW, diameter 44 m)
- Hub height: 42 m
- Total nominal power: 1,200 kW
- Operational
- Onshore wind farm
Part #2:
- City: Horsted
- Commissioning: 1996/07
- 2 turbine(s) Vestas V29/225 (power 225 kW, diameter 29 m)
- Hub height: 32 m
- Total nominal power: 450 kW
- Operational
- Onshore wind farm