| Nom | Puissance nominale totale (kW) |
Nbre de machines | Mise en service |
| Dafeng | 57 000 | 76 | 2008 |
| Dafeng | 1 500 | 1 | 2009 |
| Dafeng | 52 500 | 35 | indisp. |
| Dafeng 1500 Project | 138 000 | 92 | 2009 |
| Dafeng 1500 Project | 1 500 | 1 | 2008 |
| Dongling | 25 500 | 17 | 2006/12 |
| Dongling | 19 500 | 13 | indisp. |
| Dongyuan | 24 000 | 16 | 2007/12 |
| Dongyuan | 24 000 | 16 | indisp. |
| Huangang | 58 500 | 39 | 2006/12 |
| Huangang | 49 500 | 33 | indisp. |
| Jianggang | 6 000 | 4 | indisp. |
| Jianggang | 45 000 | 30 | indisp. |
| Rudong | 150 000 | 75 | indisp. |
| Rudong intertidal zone longyuan test wind turbine | 2 500 | 1 | 2010 |
| Wanggang | 3 750 | 5 | 2007/12 |
| Xiangshui | 2 500 | 1 | 2010 |
| Yangkou | 38 000 | 19 | indisp. |
| Yangkou | 24 000 | 12 | 2006/12 |
| Total | 723 250 | 486 |
Remarque : les totaux ne prennent pas en compte les données non disponibles.