General data

  Map  

Generalities

  • Wind farm name: S. Agata Di Puglia
  • Country: Italy
  • County / Zone: Puglia
PDF

Details


Part #1:

  • City: S. Agata Di Puglia
  • Commissioning: 1997
  • 42 turbines: Vestas V42/600 (power 600 kW, diameter 42 m)
  • Total nominal power: 25,200 kW
  • Operational
  • Onshore wind farm
  • Operator: IVPC
  • Source: http://www.ivpc.com/en/asset/

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 11.2 %
  • Expected production: 67,560 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #2:

  • City: S. Agata Di Puglia
  • Commissioning: 2007
  • 36 turbines: Vestas V80/2000 (power 2 000 kW, diameter 80 m)
  • Total nominal power: 72,000 kW
  • Operational
  • Onshore wind farm
  • Developer: Fri-El
  • Operator: EDF renewables
  • Owner: Fri-El
  • Source: http://www.fri-el.it/it/eolico/i-nostri-parchi

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 14.9 %
  • Expected production: 257,870 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #3:

  • City: S. Agata Di Puglia
  • Commissioning: 2009
  • 1 turbine: PowerWind 56 (power 900 kW, diameter 56 m)
  • Total nominal power: 900 kW
  • Operational
  • Onshore wind farm
  • Operator: EDIL Energia Sossiana

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 30.8 %
  • Expected production: 6,650 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #4:

  • City: S. Agata Di Puglia
  • Commissioning: 2010
  • 9 turbines: Gamesa G80/2000 (power 2 000 kW, diameter 80 m)
  • Total nominal power: 18,000 kW
  • Operational
  • Onshore wind farm
  • Operator: Gruppo API
  • Owner: CEF 3 Wind Energy SpA
  • Source: http://www.gruppoapi.com/settori/energia/eolico

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 25 %
  • Expected production: 107,920 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #5:

  • City: S. Agata Di Puglia
  • 11 turbines: Gamesa G87/2000 (power 2 000 kW, diameter 87 m)
  • Total nominal power: 22,000 kW
  • Operational
  • Onshore wind farm
  • Operator: Gruppo API
  • Owner: CEF 3 Wind Energy SpA
  • Source: http://www.gruppoapi.com/settori/energia/eolico

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 30.6 %
  • Expected production: 161,610 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #6:

  • City: S. Agata Di Puglia
  • Commissioning: 2010
  • 12 turbines: Gamesa G52/850 (power 850 kW, diameter 52 m)
  • Total nominal power: 10,200 kW
  • Operational
  • Onshore wind farm
  • Operator: Gruppo API
  • Owner: CEF 3 Wind Energy SpA
  • Source: http://www.gruppoapi.com/settori/energia/eolico

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 28.8 %
  • Expected production: 70,470 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #7:

  • City: S. Agata Di Puglia
  • Commissioning: 2010
  • 19 turbines: Gamesa G52/850 (power 850 kW, diameter 52 m)
  • Total nominal power: 16,150 kW
  • Operational
  • Onshore wind farm
  • Operator: Gruppo API
  • Owner: CEF 3 Wind Energy SpA
  • Source: http://www.gruppoapi.com/settori/energia/eolico

       Production forecast

  • From Wednesday, November 21 2018, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 28.8 %
  • Expected production: 111,580 kWh
  • Values from Climpact-Metnext Windcaster solution

Part #8:

  • City: S. Agata Di Puglia
  • Commissioning: 2012
  • 1 turbine: Leitwind
  • Hub height: 80 m
  • Total nominal power: 1,000 kW
  • Operational
  • Onshore wind farm
  • Developer: AREN Electric Power
  • Source: https://www.aren-ep.it/plant_view.php?lat=41.64796&lng=15.223880000000008

Localisation


Part #1:

  • Latitude: 41° 7' 58.2"
  • Longitude: 15° 18' 3.2"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #2:

  • Latitude: 41° 11' 10.2"
  • Longitude: 15° 26' 58.5"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #3:

  • Latitude: 41° 11' 11.5"
  • Longitude: 15° 26' 30.4"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #4:

  • Latitude: 41° 7' 2.8"
  • Longitude: 15° 20' 51.6"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #5:

  • Latitude: 41° 7' 33.5"
  • Longitude: 15° 20' 23.4"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #6:

  • Latitude: 41° 10' 42.6"
  • Longitude: 15° 24' 27.1"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #7:

  • Latitude: 41° 10' 42.6"
  • Longitude: 15° 24' 27.1"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #8:

  • Latitude: 41° 6' 47"
  • Longitude: 15° 22' 4"
  • Altitude: 795 m
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view


Update for this sheet: 20 August 2018
Complete/correct this sheet: