[Back to previous page]
	
		
			Generalities
						
		 | 
		
							 
				
					 | 
	
Details
Part #1: 
- City: La Mudarra, Castromonte, Peñaflor de Hornija
 - Commissioning: 

 - 2 turbines: Ecotecnia 80 1.6 (power 1 670 kW, diameter 80 m)
 - Total nominal power: 2,600 kW (downrated turbines)
 - Operational
 - Onshore wind farm
 - Developer: Bionor
 - Operator: Bionor
 - Owner: 

 
Part #2: 
- City: La Mudarra, Castromonte, Peñaflor de Hornija
 - Commissioning: 

 - 1 turbine: Ecotecnia 80 1.6 (power 1 670 kW, diameter 80 m)
 - Total nominal power: 1,300 kW (downrated turbine)
 - Operational
 - Onshore wind farm
 - Developer: Bionor
 - Operator: Bionor
 - Owner: 

 
Part #3: 
- City: La Mudarra, Castromonte, Peñaflor de Hornija
 - Commissioning: 

 - 27 turbines: Ecotecnia 80 1.6 (power 1 670 kW, diameter 80 m)
 - Total nominal power: 45,090 kW
 - Operational
 - Onshore wind farm
 - Developer: Bionor
 - Operator: Bionor
 - Owner: 

 
Localisation
Part #1: 
- Latitude: 41° 46' 53.2"
 - Longitude: -4° 56' 34.1"
 - Geodetic system: WGS84
 - Precise localization: no
 
Part #2: 
- Latitude: 41° 46' 53.2"
 - Longitude: -4° 56' 34.1"
 - Geodetic system: WGS84
 - Precise localization: no
 
Part #3: 
- Latitude: 41° 46' 53.2"
 - Longitude: -4° 56' 34.1"
 - Geodetic system: WGS84
 - Precise localization: no
 
Update for this sheet: 3 January 2024
Complete/correct this sheet: