The Wind Power is a comprehensive database of detailed raw statistics on the rapidly growing sphere of wind energy and its supporting markets. The Wind Power is a comprehensive database of detailed raw statistics on the rapidly growing sphere of wind energy and its supporting markets.
English Français Deutsch Español 

Online access Wind farms Alto Sertão 2 (Brazil)


Previous page
Sign up    Log in    Search


Alto Sertão 2 (Brazil)
Operational (383,14 MW)


Localisation  

Country Brazil
County/Zone Bahia (Nordeste)
City Caetité - Guanambi - Igaporã
Wind farm type Onshore wind farm

Key dates  

 31.86 MW commissioned
 30.24 MW commissioned
 28.56 MW commissioned
 30.24 MW commissioned
 21.84 MW commissioned
 23.52 MW commissioned
 28.56 MW commissioned
 30.4 MW commissioned
 28.56 MW commissioned
 28.56 MW commissioned
 30.24 MW commissioned
 21.84 MW commissioned
 18.48 MW commissioned
 10.08 MW commissioned
 20.16 MW commissioned

Players  

Developers

Operators

Owners
#ND
Manufacturers Alstom Power
GE Vernova

Turbines   

OperationalGE Vernova 1.6-82.5 (x 111)
OperationalAlstom Power (x 54)
OperationalGE Vernova (x 36)

Sources  

 

Details  

Part #1



PartAmetista
CityCaetite
Commissioning
Turbines17x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power28,560 kW (uprated turbines)
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 10' 19.3" - Longitude -42° 42' 0.8"
Precise localizationYes

Part #2



PartBorgo
CityCaetite
Commissioning
Turbines12x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power20,160 kW (uprated turbines)
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 30' 30.2" - Longitude -42° 35' 11.9"
Precise localizationYes

Part #3



PartCaetité
CityCaetité
Commissioning
Turbines18x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power30,240 kW (uprated turbines)
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 28' 7.9" - Longitude -42° 35' 0.8"
Precise localizationYes

Part #4



PartDa Prata
CityIgaporã
Commissioning
Turbine(s)Alstom Power
Total nominal power21,840 kW
StatusOperational
Developers/
Operator
CoordinatesLatitude -13° 57' 51.3" - Longitude -42° 38' 19.9"
Precise localizationYes

Part #5



PartDos Araças
CityCaetité
Commissioning
Turbines18x Alstom Power
Total nominal power31,860 kW
StatusOperational
Developers/
Operator
CoordinatesLatitude -14° 7' 46.5" - Longitude -42° 33' 34.7"
Precise localizationYes

Part #6



PartDourados
CityIgaporã
Commissioning
Turbines17x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power28,560 kW (uprated turbines)
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 9' 8.3" - Longitude -42° 40' 53.7"
Precise localizationYes

Part #7



PartEspigão
City#ND
Commissioning
Turbines6x GE Vernova
Total nominal power10,080 kW
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 28' 37" - Longitude -42° 35' 6.9"
Precise localizationYes

Part #8



PartMaron
CityCaetite
Commissioning
Turbines17x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power28,560 kW (uprated turbines)
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 8' 1.3" - Longitude -42° 36' 8.4"
Precise localizationYes

Part #9



PartMorrão
CityCaetité
Commissioning
Turbines18x Alstom Power
Total nominal power30,240 kW
StatusOperational
Developers/
Operator
CoordinatesLatitude -14° 5' 18.6" - Longitude -42° 40' 57.7"
Precise localizationYes

Part #10



PartPelourinho
CityIgaporã
Commissioning
Turbines13x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power21,840 kW (uprated turbines)
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 31' 45.2" - Longitude -42° 35' 12.2"
Precise localizationYes

Part #11



PartPilões
CityCaetite
Commissioning
Turbines19x GE Vernova
Total nominal power30,400 kW
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 1' 44.9" - Longitude -42° 36' 57.8"
Precise localizationYes

Part #12



PartSeraima
CityGuanambi
Commissioning
Turbines18x Alstom Power
Total nominal power30,240 kW
StatusOperational
Developers/
Operator
CoordinatesLatitude -14° 8' 50.1" - Longitude -42° 42' 42.6"
Precise localizationYes

Part #13



PartSerra do Espinhaço
City#ND
Commissioning
Turbines11x GE Vernova
Total nominal power18,480 kW
StatusOperational
Developers/
Operator
Owner
CoordinatesLatitude -14° 29' 44.6" - Longitude -42° 34' 58.2"
Precise localizationYes

Part #14



PartTanque
CityCaetité
Commissioning
Turbines17x GE Vernova 1.6-82.5 (power 1,600 kW, diameter 82.5 m)
Total nominal power28,560 kW (uprated turbines)
StatusOperational
Developers/
Operator
CoordinatesLatitude -14° 6' 9.3" - Longitude -42° 36' 38.3"
Precise localizationYes

Part #15



PartVentos do Nordeste
CityCaetité
Commissioning
Turbine(s)Alstom Power
Total nominal power23,520 kW
StatusOperational
Developers/
Operator
CoordinatesLatitude -14° 7' 10" - Longitude -42° 36' 50.6"
Precise localizationYes

Databases

     

Brazil (292.9 GW)
Americas (614.9 GW)
World (2,450.5 GW)

All databases



PDF Summary




Nearby wind farms

Alto Sertão 1 (5 km)
Alvorada (8 km)
Alto Sertão 3 (9 km)
Caetité F (11 km)
Caetité Norte e Brejinhos (11 km)
Caetité E (12 km)
Caetité D (13 km)
Caetite 2 (14 km)
Caetite 1 (15 km)
Caetité A (15 km)


Insights

Production capacity

Brazil : 34,866.0 MW (end of 2025)
Bahia (Nordeste) : 13,582.4 MW (*)


Légende

#ND : no data
(*) : according to The Wind Power database