  • City: Hamburg-Francop
  • Commissioning: 1996/09
  • 6 turbines: Micon M1500-600 (power 600 kW, diameter 43 m)
  • Total nominal power: 3,600 kW
  • Operational
  • Onshore wind farm
  • Developer: Plan 8
  • Source: http://www.plan-8.de/referenzen-windkraft.html

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 31.5 %
  • Expected production: 27,260 kWh
  • Values from Weathernews Windcaster solution

Part #2:

  • Commissioning: 1996
  • 4 turbines: (manufacturer name not available)
  • Total nominal power: 2,000 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 17,930 kWh
  • Values from Weathernews Windcaster solution

Part #3:

  • Commissioning: 1997
  • 4 turbines: (manufacturer name not available)
  • Total nominal power: 2,000 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 42.2 %
  • Expected production: 20,250 kWh
  • Values from Weathernews Windcaster solution

Part #4:

  • Commissioning: 1998
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 500 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 4,480 kWh
  • Values from Weathernews Windcaster solution

Part #5:

  • Commissioning: 1997
  • 4 turbines: (manufacturer name not available)
  • Total nominal power: 2,400 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 21,520 kWh
  • Values from Weathernews Windcaster solution

Part #6:

  • Commissioning: 1998
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 600 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 5,380 kWh
  • Values from Weathernews Windcaster solution

Part #7:

  • Commissioning: 2000
  • 2 turbines: (manufacturer name not available)
  • Total nominal power: 3,400 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 30,490 kWh
  • Values from Weathernews Windcaster solution

Part #8:

  • Commissioning: 2000
  • 2 turbines: BWU
  • Total nominal power: 1,200 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 34.6 %
  • Expected production: 9,960 kWh
  • Values from Weathernews Windcaster solution

Part #9:

  • Commissioning: 2001
  • 3 turbines: (manufacturer name not available)
  • Total nominal power: 1,800 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 31.5 %
  • Expected production: 13,630 kWh
  • Values from Weathernews Windcaster solution

Part #10:

  • Commissioning: 2002
  • 5 turbines: (manufacturer name not available)
  • Total nominal power: 3,600 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 32,280 kWh
  • Values from Weathernews Windcaster solution

Part #11:

  • Commissioning: 2003
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 600 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 5,380 kWh
  • Values from Weathernews Windcaster solution

Part #12:

  • Commissioning: 2003
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 1,200 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 10,760 kWh
  • Values from Weathernews Windcaster solution

Part #13:

  • Commissioning: 2003
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 1,000 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 17.4 %
  • Expected production: 4,180 kWh
  • Values from Weathernews Windcaster solution

Part #14:

  • Commissioning: 2004
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 1,500 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 13,450 kWh
  • Values from Weathernews Windcaster solution

Part #15:

  • Commissioning: 2009
  • 2 turbines: Enercon E126/6000 (power 6 000 kW, diameter 127 m)
  • Total nominal power: 12,000 kW
  • Operational
  • Onshore wind farm
  • Source: https://davidenergies.eu/parcs-eoliens/

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 107,600 kWh
  • Values from Weathernews Windcaster solution

Part #16:

  • Commissioning: 1991
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 150 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 34.6 %
  • Expected production: 1,250 kWh
  • Values from Weathernews Windcaster solution

Part #17:

  • Commissioning: 1993
  • 3 turbines: (manufacturer name not available)
  • Total nominal power: 450 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 4,030 kWh
  • Values from Weathernews Windcaster solution

Part #18:

  • Commissioning: 1995
  • 1 turbine: (manufacturer name not available)
  • Total nominal power: 150 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 31.9 %
  • Expected production: 1,150 kWh
  • Values from Weathernews Windcaster solution

Part #19:

  • Commissioning: 1995
  • 7 turbines: (manufacturer name not available)
  • Total nominal power: 4,200 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 37,660 kWh
  • Values from Weathernews Windcaster solution

Part #20:

  • Commissioning: 1995
  • 5 turbines: (manufacturer name not available)
  • Total nominal power: 2,500 kW
  • Operational
  • Onshore wind farm

       Production forecast

  • From Tuesday, January 21 2020, 01:00 UTC, for the coming 24 hours:
  • Expected load rate: 37.4 %
  • Expected production: 22,420 kWh
  • Values from Weathernews Windcaster solution

Part #21:

  • City: Hamburg-Francop
  • 3 turbines: Enercon E40/500 (power 500 kW, diameter 40 m)
  • Total nominal power: 1,500 kW
  • Operational
  • Onshore wind farm

Part #22:

  • City: Hamburg-Francop
  • 4 turbines: Enercon E40/600 (power 600 kW, diameter 40 m)
  • Total nominal power: 2,400 kW
  • Operational
  • Onshore wind farm

Part #23:

  • City: Hamburg-Francop
  • 1 turbine: Südwind S46/600 (power 600 kW, diameter 46 m)
  • Total nominal power: 600 kW
  • Operational
  • Onshore wind farm

Part #24:

  • City: Hamburg-Francop
  • 1 turbine: Vestas
  • Operational
  • Onshore wind farm

Part #25:

  • City: Hamburg-Francop
  • 3 turbines: Neg Micon
  • Dismantled
  • Onshore wind farm

Localisation


Part #1:

  • Latitude: 53° 30' 1.1"
  • Longitude: 9° 51' 23.9"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #2:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #3:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #4:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #5:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #6:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #7:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #8:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #9:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #10:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #11:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #12:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #13:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #14:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #15:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #16:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #17:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #18:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #19:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #20:

  • Latitude: 53° 30' 0"
  • Longitude: 9° 50' 59.9"
  • Geodetic system: WGS84
  • Precise localization: no

Part #21:

  • Latitude: 53° 30' 1.1"
  • Longitude: 9° 51' 23.9"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #22:

  • Latitude: 53° 30' 1.1"
  • Longitude: 9° 51' 23.9"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #23:

  • Latitude: 53° 30' 1.1"
  • Longitude: 9° 51' 23.9"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #24:

  • Latitude: 53° 30' 1.1"
  • Longitude: 9° 51' 23.9"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view

Part #25:

  • Latitude: 53° 30' 1.1"
  • Longitude: 9° 51' 23.9"
  • Geodetic system: WGS84
  • Precise location: yes
  • Google Maps view


Update for this sheet: 10 January 2020
Complete/correct this sheet:



The Wind Power
contact@thewindpower.net
All rights reserved - 2005-2020

General Terms and Conditions of Sale - Partners
NEWSLETTER