Part #1:
- Part: Campagne Spêches
- City: Sombreffe
- Commissioning:

- 4 turbines: GE Energy 1.5sl (power 1 500 kW, diameter 77 m)
- Hub height:

- Total nominal power: 6,000 kW
- Operational
- Onshore wind farm
- Developer: Eneco
Part #2:
- Part: Campagne Spêches - Extension
- City: Gembloux, Sombreffe
- Commissioning:

- 2 turbines: Repower MD77 (power 1 500 kW, diameter 77 m)
- Hub height:

- Total nominal power: 3,000 kW
- Operational
- Onshore wind farm
- Developer: Eneco
Localisation
Part #1:
Part #2:
Pictures

Author: Gabriel - License: All right reserved
Picture reference: 16843 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16844 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16845 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16846 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16847 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16848 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16849 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16850 - Date: 2025

Author: Gabriel - License: All right reserved
Picture reference: 16851 - Date: 2025
Update for this sheet: 0
Complete/correct this sheet: