Ullerup (Thisted) (Denmark)| Ullerup (Thisted) (Denmark) |
|
| Operational (1,2 MW) - Dismantled (0,675 MW) |

| Country | Denmark |
| County/Zone | Thisted (Nordjylland) |
| City | Ullerup |
| Wind farm type | Onshore wind farm |

![]() | 0.675 MW commissioned |
![]() | 0.6 MW commissioned |
![]() | 0.6 MW commissioned |
![]() | 0.675 MW decommissioned |

| Developer | #ND |
| Operator | #ND |
| Owner | #ND |
| Manufacturer |
|

| Operational | Vestas V42/600 (x 2) |
| Dismantled | Vestas V27/225 (x 3) |

![]() | |

| City | Ullerup |
| Commissioning | ![]() |
| Turbine | 1x Vestas V42/600 (power 600 kW, diameter 42 m) |
| Hub height | ![]() |
| Total nominal power | 600 kW |
| Status | Operational |
| Coordinates | Latitude 56° 46' 11.3" - Longitude 8° 27' 15.4" |
| Precise localization | No |
| City | Ullerup |
| Commissioning | ![]() |
| Turbine | 1x Vestas V42/600 (power 600 kW, diameter 42 m) |
| Hub height | ![]() |
| Total nominal power | 600 kW |
| Status | Operational |
| Coordinates | Latitude 56° 46' 11.3" - Longitude 8° 27' 15.4" |
| Precise localization | No |
| City | Ullerup |
| Commissioning | ![]() |
| Turbines | 3x Vestas V27/225 (power 225 kW, diameter 27 m) |
| Hub height | ![]() |
| Total nominal power | 675 kW |
| Status | Dismantled (2015/06) |
| Coordinates | Latitude 56° 46' 11.3" - Longitude 8° 27' 15.4" |
| Precise localization | No |
Databases ![]() Denmark (10.1 GW) Europe (654.1 GW) World (2,450.5 GW) All databases |
||
PDF Summary
|
||
| Nearby wind farms Heltborg (2 km) Gisserbaek (2 km) Hurup (3 km) Grurup (3 km) Ettrup (4 km) Villerslev (6 km) Hassing (Thisted) (6 km) Adbol (6 km) Gundtoft (7 km) Morup Molle (7 km) | ||
|
Insights Production capacity Denmark : 7,508.0 MW (end of 2025) Thisted (Nordjylland) : 360.1 MW (*) |
||
|
Légende #ND : no data (*) : according to The Wind Power database |
||
|
Update for this sheet 26 April 2019 |
||