[Back to previous page]
Generalities
|
|
Details
Part #1:
- City: Meckel
- Commissioning:

- 1 turbine: Nordex N54/1000 (power 1 000 kW, diameter 54 m)
- Hub height:

- Total nominal power: 1,000 kW
- Operational
- Onshore wind farm
Production forecast
- From Thursday, March 23 2023, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 100 %
- Expected production: 24,010 kWh
- Values from Weathernews Windcaster solution
Part #2:
- City: Gilzem
- Commissioning:

- 1 turbine: Repower MD77 (power 1 500 kW, diameter 77 m)
- Total nominal power: 1,500 kW
- Operational
- Onshore wind farm
Production forecast
- From Thursday, March 23 2023, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 96 %
- Expected production: 34,540 kWh
- Values from Weathernews Windcaster solution
Part #3:
- City: Meckel
- Commissioning:

- 1 turbine: Senvion MM82/2050 (power 2 050 kW, diameter 82 m)
- Hub height:

- Total nominal power: 2,050 kW
- Operational
- Onshore wind farm
- Developer: UTEC
- Operator: Siemens-Gamesa
- Owners:
/
- Source:

Production forecast
- From Thursday, March 23 2023, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 98.3 %
- Expected production: 48,360 kWh
- Values from Weathernews Windcaster solution
Part #4:
- City: Gilzem
- Commissioning:

- 1 turbine: Vestas V90/2000 (power 2 000 kW, diameter 90 m)
- Hub height:

- Total nominal power: 2,000 kW
- Operational
- Onshore wind farm
- Developer: SeeBA EnergyFarming
- Source:

Production forecast
- From Thursday, March 23 2023, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 87.6 %
- Expected production: 42,030 kWh
- Values from Weathernews Windcaster solution
Part #5:
- City: Meckel
- Commissioning:

- 1 turbine: Repower MD77 (power 1 500 kW, diameter 77 m)
- Total nominal power: 1,500 kW
- Operational
- Onshore wind farm
- Developer: UTEC
- Operator: Siemens-Gamesa
- Owners:
/
- Source:

Part #6:
- City: Meckel, Gilzem
- Commissioning:

- 3 turbines: Repower MD77 (power 1 500 kW, diameter 77 m)
- Hub height:

- Total nominal power: 4,500 kW
- Operational
- Onshore wind farm
- Developer: UTEC
- Source:

Part #7:
- City: Meckel
- Commissioning:

- 1 turbine: Enercon E82/2300 (power 2 300 kW, diameter 82 m)
- Hub height:

- Total nominal power: 2,300 kW
- Operational
- Onshore wind farm
Part #8:
- City: Meckel
- Commissioning:

- 1 turbine: Nordex N117/2400 (power 2 400 kW, diameter 117 m)
- Hub height:

- Total nominal power: 2,400 kW
- Operational
- Onshore wind farm
Localisation
Part #1:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #2:
- Latitude: 49° 52' 42"
- Longitude: 6° 30' 56.6"
- Geodetic system: WGS84
- Precise localization: no
Part #3:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #4:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #5:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #6:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #7:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #8:
- Latitude: 49° 52' 40.4"
- Longitude: 6° 30' 54.3"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Update for this sheet: 8 July 2022
Complete/correct this sheet: