[Back to previous page]
Generalities
|
|
Details
Part #1:
- City: Titting
- Commissioning:

- 8 turbines: Nordex N117/2400 (power 2 400 kW, diameter 117 m)
- Hub height:

- Total nominal power: 19,200 kW
- Operational
- Onshore wind farm
- Developer: Naturstrom Anlagen GmbH
- Source:

Part #2:
- City: Titting
- Commissioning:

- 2 turbines: Vensys 112 (power 2 500 kW, diameter 112.5 m)
- Hub height:

- Total nominal power: 5,000 kW
- Operational
- Onshore wind farm
- Developer: Sachs Regenerative Energie
- Source:

Part #3:
- City: Titting
- Commissioning:

- 2 turbines: Senvion 3.2M114 (power 3 200 kW, diameter 114 m)
- Hub height:

- Total nominal power: 6,400 kW
- Operational
- Onshore wind farm
- Developer: Naturstrom Anlagen GmbH
- Source:

Part #4:
- City: Titting
- Commissioning:

- 1 turbine: Senvion 3.2M114 (power 3 200 kW, diameter 114 m)
- Hub height:

- Total nominal power: 3,200 kW
- Operational
- Onshore wind farm
- Developer: Naturstrom Anlagen GmbH
- Source:

Part #5:
- City: Titting
- Commissioning:

- 4 turbines: Nordex N117/2400 (power 2 400 kW, diameter 117 m)
- Hub height:

- Total nominal power: 9,600 kW
- Operational
- Onshore wind farm
Localisation
Part #1:
- Latitude: 49° 1' 47.2"
- Longitude: 11° 12' 58.4"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #2:
- Latitude: 49° 1' 31.5"
- Longitude: 11° 12' 51.2"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #3:
- Latitude: 49° 2' 54.7"
- Longitude: 11° 13' 48.6"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #4:
- Latitude: 49° 1' 35.1"
- Longitude: 11° 12' 31.6"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #5:
- Latitude: 49° 1' 31.5"
- Longitude: 11° 12' 51.2"
- Geodetic system: WGS84
- Precise localization: no
Update for this sheet: 17 November 2020