[Back to previous page]
	
		
			Generalities
						
		 | 
		
							 
				
					 | 
	
Details
Part #1: 
- City: Laar
 - Commissioning: 

 - 4 turbines: Senvion MM92/2050 (power 2 050 kW, diameter 92.5 m)
 - Hub height: 

 - Total nominal power: 8,200 kW
 - Operational
 - Onshore wind farm
 
Part #2: 
- City: Emlichheim
 - Commissioning: 

 - 10 turbines: Enercon E66/1800 (power 1 800 kW, diameter 66 m)
 - Hub height: 

 - Total nominal power: 18,000 kW
 - Operational
 - Onshore wind farm
 
Part #3: 
- City: Emlichheim
 - Commissioning: 

 - 2 turbines: Tacke 1.5s (power 1 500 kW, diameter 70.5 m)
 - Hub height: 

 - Total nominal power: 3,000 kW
 - Dismantled (2020/12)
 - Onshore wind farm
 
Part #4: 
- City: Emlichheim
 - Commissioning: 

 - 6 turbines: Enercon E115/3000 (power 3 000 kW, diameter 115.7 m)
 - Hub height: 

 - Total nominal power: 18,000 kW
 - Operational
 - Onshore wind farm
 - Developer: BVT
 
Part #5: 
- City: Emlichheim
 - Commissioning: 

 - 2 turbines: Tacke 1.5s (power 1 500 kW, diameter 70.5 m)
 - Hub height: 

 - Total nominal power: 3,000 kW
 - Dismantled (2020/12)
 - Onshore wind farm
 
Localisation
Part #1: 
Part #2: 
- Latitude: 52° 32' 29.6"
 - Longitude: 6° 53' 34.4"
 - Geodetic system: WGS84
 - Precise localization: no
 
Part #3: 
- Latitude: 52° 34' 53.3"
 - Longitude: 6° 45' 28.6"
 - Geodetic system: WGS84
 - Precise localization: no
 
Part #4: 
- Latitude: 52° 38' 36.9"
 - Longitude: 6° 48' 23.7"
 - Geodetic system: WGS84
 - Precise localization: no
 
Part #5: 
- Latitude: 52° 38' 11.1"
 - Longitude: 6° 48' 45.6"
 - Geodetic system: WGS84
 - Precise localization: no
 
Update for this sheet: 1 September 2022
Complete/correct this sheet: