[Back to previous page]
Generalities
|
|
Details
Part #1:
- City: Balje
- Commissioning:

- 7 turbines: Bonus B62/1300 (power 1 300 kW, diameter 62 m)
- Hub height:

- Total nominal power: 9,100 kW
- Operational
- Onshore wind farm
- Developer: N.prior energy
- Operator: N.prior energy
- Owner:

Production forecast
- From Saturday, March 06 2021, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 21.3 %
- Expected production: 46,600 kWh
- Values from Weathernews Windcaster solution
Part #2:
- City: Balje
- Commissioning:

- 3 turbines: Enercon E40/500 (power 500 kW, diameter 40 m)
- Hub height:

- Total nominal power: 1,500 kW
- Operational
- Onshore wind farm
- Developer: PN Power Plants AG
- Source:

Production forecast
- From Saturday, March 06 2021, 01:00 UTC, for the coming 24 hours:
- Expected load rate: 21.1 %
- Expected production: 7,590 kWh
- Values from Weathernews Windcaster solution
Localisation
Part #1:
- Latitude: 53° 48' 51.1"
- Longitude: 9° 4' 14.4"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Part #2:
- Latitude: 53° 49' 3.4"
- Longitude: 9° 4' 17.5"
- Geodetic system: WGS84
- Precise location: yes
- Google Maps view
Update for this sheet: 21 July 2020
Complete/correct this sheet: